A flexible budget is a powerful tool for evaluating financial performance. Unlike a static budget, which remains unchanged regardless of actual activity levels, a flexible budget adjusts to reflect variations in sales or production volume. This makes it a much more accurate measure of managerial effectiveness. This article will explore what a flexible budget performance report compares, how it's created, and its benefits.

What Does a Flexible Budget Performance Report Compare?

A flexible budget performance report compares actual results to budgeted amounts adjusted for the actual activity level. This is the key difference from a static budget report. A static budget compares actual results to a single, predetermined budget regardless of how many units were actually sold or produced. A flexible budget, however, recalculates the budget based on the actual activity, providing a more insightful comparison.

The report typically compares:

  • Sales Revenue: Actual sales revenue versus the flexible budget's projected revenue based on actual sales volume.
  • Variable Costs: Actual variable costs (directly tied to production volume, such as direct materials and labor) against the flexible budget's projection for the actual volume.
  • Fixed Costs: Actual fixed costs (costs that remain relatively constant regardless of volume, like rent and salaries) versus the budgeted fixed costs.
  • Contribution Margin: The difference between sales revenue and variable costs, both actual and budgeted. This shows the amount available to cover fixed costs and generate profit.
  • Net Operating Income: The final profit or loss after deducting all costs (variable and fixed) from revenue.

How to Create a Flexible Budget Performance Report

Creating a flexible budget performance report involves several steps:

  1. Determine the Activity Level: Identify the actual level of activity (e.g., units sold, hours worked) for the period being analyzed.

  2. Prepare a Flexible Budget: Use the predetermined budget's variable cost per unit and fixed cost figures to create a new budget based on the actual activity level. For example, if the static budget was based on 10,000 units and the actual sales were 12,000 units, the flexible budget will recalculate costs and revenue based on 12,000 units.

  3. Gather Actual Results: Collect data on actual sales revenue and all costs incurred during the period.

  4. Compare Actual to Flexible Budget: Calculate the variances (differences) between actual results and the flexible budget figures for each revenue and cost item. Variances can be expressed in dollars and/or as percentages.

  5. Analyze Variances: Investigate the reasons behind significant variances. Were there unexpected increases in material costs? Was there less efficient labor utilization? This analysis helps identify areas needing improvement.

Example of a Flexible Budget Performance Report

Let's assume a company budgeted for 10,000 units but actually sold 12,000 units. Here's a simplified example of how the flexible budget report might look:

Item Static Budget (10,000 units) Flexible Budget (12,000 units) Actual Results (12,000 units) Variance (Actual - Flexible)
Sales Revenue $100,000 $120,000 $115,000 -$5,000
Variable Costs $60,000 $72,000 $75,000 $3,000
Fixed Costs $20,000 $20,000 $22,000 $2,000
Contribution Margin $40,000 $48,000 $40,000 -$8,000
Net Operating Income $20,000 $28,000 $18,000 -$10,000

Benefits of Using a Flexible Budget Performance Report

  • Improved Accuracy: Provides a more realistic comparison of performance by adjusting for actual activity levels.
  • Better Management Control: Highlights variances between actual and budgeted figures, enabling managers to identify areas needing attention.
  • Enhanced Decision-Making: Facilitates more informed decisions by providing a clearer understanding of cost and revenue drivers.
  • Increased Accountability: Helps hold managers accountable for performance by showing how well they managed resources given the actual activity level.

Conclusion

A flexible budget performance report offers a more accurate and insightful analysis of financial performance than a static budget. By comparing actual results to a budget adjusted for the actual activity level, it allows managers to better understand cost drivers, improve efficiency, and make more informed decisions. Implementing a flexible budgeting system is a valuable step in enhancing financial control and profitability.